Compressed air is one of the most expensive utilities in a plant, and leaks run 24 hours a day. Find the leakage % from a load-unload test, or add up leaks by hole size, and see the kW and rupees wasted every year.
With all air users stopped (e.g. during a lunch break or shift change), time how long the compressor stays on load and off load. Average a few cycles.
Leakage above 10 % is worth a leak survey: tag, repair and re-test.
Want the full picture, with stack loss, blowdown, condensate and a BEE-style report? Run a complete audit free in Enerzivo.
Formulas
T = average load time, t = average unload time, with all air users stopped. Unload power is ignored, so the result is slightly conservative.
Worked example
A 75 kW screw compressor with a capacity of 10 m³/min stays on load for 20 seconds and off load for 40 seconds with the plant idle. Leakage = 20 ÷ 60 = 33 %, or 3.3 m³/min of air. Wasted energy = 75 × 0.33 × 8,000 h = 2,00,000 kWh a year, which is about Rs 16 lakh a year at Rs 8 per kWh.
How to cut compressed air leaks
- Run a leak survey with an ultrasonic detector, tag every leak, repair them and re-test the leakage %.
- Reduce the header pressure to the minimum the end users need: each 1 bar less saves about 6-7 % of compressor power, and leaks fall too.
- Isolate idle machines and sections with solenoid valves, and replace open blow-offs with engineered nozzles.
- Fit zero-loss condensate drains in place of timer drains or open valves.
- Repeat the survey every quarter, because leaks come back.